Actualities
News
In March 2012 CZ Mont awarded contract from Metso (Finland) company for
assembly of 70MWth Hybex type boiler. BFB (bubbling fluidized bed) boiler will
provide heat and electricity for Jelgava town in Latvia. Scope of supply
consists of boiler assembly, as well as connecting pipings, fuel feeding,
deashing and flue gas cleaning. Total assembled weight of pressure and non
pressure parts is 1100 tons. Terms of realisation 07/2012 till 03/2013.
The Actual Supporting Projects being executed by CZ MONT, s.r.o. :
| Contract: |
Power Station Belchatow, Poland |
| Duration: |
1/2012–12/2012 |
| Subject: |
Assembly and disassembly of membrane walls over the hopper, including
displaced 8 pcs powder burners – about 5,500 of pressure joints,
disassembly and exchange of buckstays about 94 000 kg – Boiler K7,
K8 400MW |
| Purchaser: |
STEINMULLER |
| Contract: |
TEKO Košice, Slovakia |
| Duration: |
6/2011–5/2012 |
| Subject: |
Assembly of the granulation of the boiler to burn coal with the following
parameters: rated power boiler 130 t / h, nominal steam temperature of
540 C, nominal pressure superheated steam at 13.64 MPa, the total
weight of pressure and non-pressure parts of 2000 tonnes |
| Purchaser: |
IEG |
| Contract: |
Zona Franca Punta Pereira, Colonia, Uruguay |
| Duration: |
5–12/2012 |
| Subject: |
Welding and assembly works on installation of boiler |
| Purchaser: |
HM Ostrava |
| Contract: |
Moorburg, Germany |
| Duration: |
2012 |
| Subject: |
Welding and assembly works on installation of supercritical boiler
800 MW |
| Purchaser: |
HM Ostrava |
| Contract: |
Rotterdamm, Nedherland |
| Duration: |
2011–2012 |
| Subject: |
Welding and assembly works on installation of supercritical boiler
800 MW |
| Purchaser: |
HM Ostrava |
| Contract: |
Walsum, Germany |
| Duration: |
4–12/2012 |
| Subject: |
Welding and assembly works on installation of boiler |
| Purchaser: |
Bilfinger |
| Contract: |
Crescenino, Italy |
| Duration: |
1–8/2012 |
| Subject: |
Assembly of biomass boiler |
| Purchaser: |
Oschatz |
| Contract: |
Port Talbot, Wales |
| Duration: |
2–12/2012 |
| Subject: |
Assembly and diassembly works on 3 boilers |
| Purchaser: |
Oschatz |
| Contract: |
Wilhelmshaven, Germany |
| Duration: |
2010–2011 |
| Subject: |
Welding and assembly works on installation of supercritical boiler
800 MW |
| Purchaser: |
HM Ostrava |
| Contract: |
Kladno, ČR |
| Duration: |
4–12/2012 |
| Subject: |
Welding and assembly works on assembly of boiler CFB 100 MW |
| Purchaser: |
HM Ostrava |
| Contract: |
Landskorna, Sweden |
| Duration: |
2011–2012 |
| Subject: |
Welding and assembly works on piping system |
| Purchaser: |
VIFLOW |
| Contract: |
Örnsköldsvik, Sweden |
| Duration: |
2011–2012 |
| Subject: |
Works on turning machines |
| Purchaser: |
VIFLOW |
| Contract: |
SES, a.s. |
| Duration: |
2010–2012 |
| Subject: |
Welding and assembly works on pressure systems |
| Purchaser: |
SES, a.s. |
| Contract: |
MCE |
| Duration: |
2006–2012 |
| Subject: |
Welding and assembly works |
| Purchaser: |
MCE Bilfinger |